Sizing the equipment ground wire

A wire equipment ground is sized from Table 250.122 by the breaker or fuse protecting the circuit. If the circuit wires are made larger, for example to reduce voltage drop, the ground wire must be enlarged in proportion.

What the code requires

A wire-type equipment grounding conductor must be at least the size in Table 250.122 for the breaker or fuse ahead of it, but it never has to be larger than the circuit conductors. Selected copper sizes, with aluminum or copper-clad aluminum in parentheses: 15 A, 14 AWG (12); 20 A, 12 AWG (10); 60 A, 10 AWG (8); 100 A, 8 AWG (6); 200 A, 6 AWG (4); 300 A, 4 AWG (2); 400 A, 3 AWG (1).

Larger ratings: 500 A, 2 AWG (1/0); 600 A, 1 AWG (2/0); 800 A, 1/0 (3/0); 1000 A, 2/0 (4/0); 1200 A, 3/0 (250 kcmil). Where parallel conductors run in multiple raceways and a wire-type ground is used, each raceway gets one, sized from the breaker or fuse rating for the whole circuit.

If the hot conductors are made larger for any reason other than the temperature and bundling corrections in 310.15(B) and (C), such as voltage drop, the wire ground must be increased in proportion to the increase in circular-mil area.

One ground may serve several circuits in the same raceway, cable, trench or cable tray, sized for the largest breaker or fuse. For feeder taps, the ground is sized from the breaker or fuse ahead of the feeder but need not be larger than the tap conductors.

On the job

  • A 20 A circuit upsized from 12 to 10 AWG for voltage drop needs its ground upsized to 10 AWG as well.
  • An undersized ground on a 60 A EV charger or subpanel feeder is a common correction. 10 AWG copper is the minimum.

Exceptions that matter

  • A qualified person may size the ground to provide an effective ground-fault path under 250.4(A)(5) or (B)(4) instead of increasing it in proportion.

Related sections

Where this comes from

0/300

Answers come from this library only and are written by AI. They can be wrong, so check the cited section and confirm with your building department.

San Clemente · South OC to North County San Diego

Send a photo. Get a real answer.

Text is fastest, and a photo quote is free. Call if it is urgent, if you smell something burning, or if a breaker will not reset.

CSLB #354550 · C-10 Electrical · Licensed since 1978 · $25,000 contractor's bond