NEC 230.95 · Commercial

Ground-fault protection on large commercial services

Solidly grounded wye services over 150 V to ground and not over 1,000 V phase-to-phase, typically 480Y/277 V, need ground-fault protection of equipment on each service disconnect rated 1,000 A or more, tested when first installed.

What the code requires

Ground-fault protection of equipment (GFPE) is required on solidly grounded wye services of more than 150 V to ground but not over 1,000 V phase-to-phase, for each service disconnect rated 1,000 A or more. In practice that means 480Y/277 V services. A 208Y/120 V service does not trigger it, because it is not over 150 V to ground.

A disconnect's rating is the largest fuse that can be installed, or the highest continuous trip setting the breaker is rated for or can be adjusted to.

The protection must open all ungrounded conductors. The maximum setting is 1,200 A, with a maximum time delay of 1 second for ground-fault currents of 3,000 A or more. With a switch and fuses, the fuses must clear any current above the switch's interrupting capacity before the ground-fault protection opens the switch.

The system must be performance tested when first installed, by qualified persons using primary current injection per the equipment instructions, with a written record available to your inspector.

On the job

  • No primary-injection test record at final inspection is a common holdup.
  • Splitting a service into two to six smaller disconnects, each under 1,000 A, can avoid the requirement.
  • The rule looks at the largest fuse that fits or the highest setting the breaker allows, not just the setting used.

Exceptions that matter

  • Not required for a continuous industrial process where a nonorderly shutdown would add hazards.

Related sections

Where this comes from

0/300

Answers come from this library only and are written by AI. They can be wrong, so check the cited section and confirm with your building department.

San Clemente · South OC to North County San Diego

Send a photo. Get a real answer.

Text is fastest, and a photo quote is free. Call if it is urgent, if you smell something burning, or if a breaker will not reset.

CSLB #354550 · C-10 Electrical · Licensed since 1978 · $25,000 contractor's bond